|
|
|
CHAIRMAN'S REPORT
|
|
|
|
|
|
RMA – HARBOUR USER GROUP Hi everyone, Here are some notes which I made following the Harbour Users Group Meeting held on Wednesday 19th March; the meeting was chaired by Councillor Roger Latchford. Dredging The dredger has arrived in the harbour (the tug pulling it ran aground and the dredger ran into the back of the tug!) but has broken down. Repairs are to be completed and work restarted after Easter. It is likely that only the entrance and a limited area of the Eastern Marina will be dredged. Tenders have not yet been obtained for the 3 year dredging contract. Flares Estuary Services (Pilot Boats) will organise dates when the weather is better. Wind Farms It is unlikely that the Royal Harbour will be used as a base during construction for it would cost £40 million to build the necessary facilities. TDC hope that Ramsgate will become the Operation & Maintenance Base. Some part of the boat yard may be lost but more space can be found closer to the cliffs. Other matters (a) Two sets of recycling bins have been provided for 2008 (b) Work is in progress to provide signs for the safety ladders and paint adjacent steel piles red. (c) A new oil recycling facility is to be ordered. (d) The pump out facility is to be installed by the end of April. (e) An automatic fuel pump operated by credit card is to be provided by the end of the summer. (f) Estuary Services are to buy a new pilot boat and increase their annual trips from 850 to 1500 due to the new pilotage arrangements in the Thames. (g) The possibility of fitting an electrically operated system to the security gate near the dock office is to be investigated because the current system does not lock the gate. (h) An apron for guide dogs is to be fitted to the car park entrance barrier. (i) Southern Water no longer permit permanent hose pipes to be fitted to the Marina standpipes because of the risk of contamination. Individual Owners will need to use their own portable hoses.
The following points relevant to the RMA were discussed at the Harbour Liaison Committee on Thursday 22nd June.
1. Electrics.
The upgrade of the marina electrics is almost complete. One pedestal
with four sockets has been provided on the Eastern Marina southern
breakwater and a second is on order. The cost of supplying electricity
to the Marina exceeds the cost and meters will eventually be
installed. There are berth holders who do not pay for electricity but
do use it and action is to be taken to stop this practice. Meters will
be individual and the outlet socket locked to prevent theft of
electricity.
2. Disabled Parking
Additional disabled parking to be identified;
the use of the parking space adjacent to the East Inner Marina gate is
for loading/ unloading only.
3. Loading Bay
A loading / unloading bay adjacent to the East
Inner Marina gate is to be established, limited to 30 minutes,
monitored by the Dock Office.
4. Dredging
Dredging by the Ramsgate dredger will continue
but otherwise dredging by external companies is complete for this
year. All marinas (including the Inner Marina)require dredging and
quotations are being obtained to carry this out over a 3 year period.
5. Cleanliness
Undertakings were given that the Inner Marina
would be continuously be kept clean throughout the season. (It is much
better than a couple of weeks ago).
6. East Marina
More berths have been taken up by small fishing
craft and commercial craft in the Eastern Marina causing lack of space
for temporary mooring by Inner Marina boats working the gate
opening times. It is recognised by the Harbour Master that a berth
management system for all outer marina berths is a priority - but no
date for resolution given.
7. Transmanche Marinas
Letter and questionnaire issued to all berth
holders by the Harbour. The EU is funding a study by Consultants to
identify ways to encourage reciprocal visits between the Transmanche
Marinas. RMA suggested that 50% discounts on mooring fees (outwith
the main season) to visitors to and from other Transmanche marinas
could be funded by the EU instead. May be considered.
8. Trolleys
The Harbour Master assured the RMA that there
would be an adequate supply of trolleys after the Power Boat weekend
(Normally they all disappear with the power craft)
9. Dover Marina
It was reported that Dover Harbour are looking
at proposals to extend commercial activities at the Western Docks and
might need to fill in one of the marinas. The lost berths could be
replaced by a move to Ramsgate.
Regards
Brian
|
|
|
|
|
|
From Brian Marchbank
Sent: Tuesday, April 04, 2006 4:55 PM
Subject: RAMSGATE MARINA ASSOCIATION
Dear Dominic,
There is one further point which Tim and I
should have discussed with you when we met last Thursday.
There is a regular problem in the season by
visitors occupying permanent berth-holders spaces in the Outer West
Marina. As you know, the Dockmaster simply tells visitors to find a
space and although the permanent berth-holders spaces are marked, when
space is tight then visitors use them. This gives rise to
confrontation and anger when the permanent berth-holder returns from
fishing or a cruise.
The short term solution, adopted in many
marinas, would be to adopt a red/green system. A red board is fixed to
the end of the berth and states "occupied". This board can
be covered by a green board stating "free" hung on a couple
of pins. Berth-holders on an extended cruise could phone the
Dockmaster the day before they return to have the green board removed.
Sometimes this system is augmented by a cord across the entrance to
the berth with a board stating "reserved".Could you please
give consideration to this issue.
Some Marinas actually give a rebate in mooring
fees to permanent berth-holders who advise them that their berth will
be unoccupied.
The longer term solution now used in the many
modern Marinas is a PC based berth management system; Breskens has the
best example I have experienced. A plan of the Marina is loaded into a
PC - I am sure that the software package is readily available - and
this enables berth availability to be accurately managed. Visitors
call by vhf or phone in advance and are allocated a specific berth
together with other instructions such as berthing side to enable ropes
and fenders to be readied. Something for Ramsgate to aspire to?
Regards
Brian
From: "Dominic Evans" <Dominic.Evans@thanet.gov.uk> To: "Brian Marchbank" <bmmarchbank@rya-online.net> Sent: Tuesday, April 04, 2006 7:47 PM Subject: Re: RAMSGATE MARINA ASSOCIATION
Dear Brian
Thank you for your email, the system of allocation of berths for visitors is under review, and methods of indicating fee berths, though no decision has yet been reached on which system we are going to use. Thank you for your continued interest in the marina, feed back from users is always very welcome, especially when they pass on details of systems that work in other marinas.
Kind regards
Dominic Evans General Manager/Harbourmaster Port of Ramsgate
|
|
| UPDATED-23/03/2008 10:30 | |
|
|